Pandemic Delays Planning for Third Span Crossing Chesapeake Bay

A study on adding a third span to the existing Chesapeake Bay Bridge to ease traffic has stalled because of COVID-19, but there are plans to eventually move forward.

In-person public hearings for a study on the environmental impacts of a new span cannot take place as required by federal guidelines due to the pandemic, but the Maryland Department of Transportation said the project is still on budget.

With traffic along the bridge expected to get worse, Gov. Lawrence J. Hogan Jr. (R) ordered the study back in 2016, expecting it to take four years and $5 million to complete. Once the study is completed, it could then take an additional three to five years if officials decide to consider a no-build alternative plan for the project.

MDOT said it expects to release more details on a schedule for hearings to begin the environmental study in the near future.

As part of Maryland Matters’ content sharing agreement with WTOP, we feature this article from Melissa Howell. Click here for the WTOP News website.

REPUBLISHING TERMS

Our stories may be republished online or in print under Creative Commons license CC BY-NC-ND 4.0. We ask that you edit only for style or to shorten, provide proper attribution and link to our website. Please see our republishing guidelines for use of photos and graphics.

If you have any questions, please email [email protected].

To republish, copy the following text and paste it into your HTML editor.

License

Creative Commons License AttributionCreative Commons Attribution
Pandemic Delays Planning for Third Span Crossing Chesapeake Bay